NEMO Committee releases full text of SDAC Fallback Manual v1.5, confirming 3 November 2026 applicability and detailing decoupling procedures
ImplementationThe primary source provides the complete content of SDAC Fallback Manual Version 1.5 (previously only an excerpt was available), confirming the same applicability date of 03/11/2026 and the same 'Highlighted changes versus previous version' label without itemizing the specific deltas versus v1.4. The new material adds extensive procedural detail already implicit in the prior record: full timelines for Partial Decoupling (CZC-related, during coupling, known in advance), Full Decoupling, associated market messages (SDAC_ExC series), interconnector-specific fallback allocation tables (Shadow Auctions via JAO, Intraday market, Nordic-Baltic regional coupling, back-to-owner), and regional annexes for Core, IBWT, Nordic-Baltic, Poland and BG-RO.
This fuller text operationalizes the governance update already flagged in the prior event: it specifies exact deadlines (11:30, 13:00, 14:20, 10:30 CET) and allocation mechanisms NEMOs, TSOs and JAO must follow for each SDAC interconnector during decoupling events, which is directly relevant to price formation continuity, cross-border capacity allocation and operational security ahead of the 3 November 2026 applicability date.
The additional content confirms rather than alters the market-design significance already identified: this remains a procedural/operational codification of existing SDAC fallback concepts rather than a substantive reform. The detailed interconnector-by-interconnector fallback tables (Shadow Auctions, Intraday reallocation, Nordic-Baltic regional coupling, back-to-owner) and regional annex structures (Core, IBWT, Nordic-Baltic, Poland, RO-BG) suggest version 1.5 is largely a consolidation/clarification exercise, though without an explicit changelog against v1.4 it remains impossible to assess whether any deadline, allocation rule or regional annex was materially altered versus the prior version. Market participants should still seek the dedicated change-log to confirm whether any of the timelines or fallback allocation assignments shown here differ from v1.4.
CACM Regulation (Capacity Allocation and Congestion Management)
SDAC Fallback Manual Version 1.5 becomes applicable · 3 Nov 2026
Primary sources
SDAC Fallback Manual - updated version
Open primary source ↗