JAO's v5 Nomination Information document re-confirmed with no substantive content changes versus prior baseline

Implementation
ENERGY MARKETSMULTI-TIMEFRAMEnomination_rulescross_border_capacity_allocationtransmission_rightseligible_person_designationsdac_nomination_deadlinesbalance_responsible_party_requirements
1Problem identified
2Consultation
3Proposal
4Regulatory review
5Decision
6Implementation
7Go-live
8Market impact
What changed

The primary source is the same JAO 'Nomination Information' v5 document (internal date 09/10/2026, public release 2026-11-05) already captured as the baseline event: identical per-country/TSO nomination prerequisites, the eight nomination principles (A-to-A through M-to-N), the border-specific nomination deadline tables for long-term, daily, intraday and shadow auctions, and the SDAC NEMO-message deadline-postponement table. No new border, deadline, principle, or legal-prerequisite appears in this text beyond what was already recorded.

Why it matters

Because this is the same reference document market participants, BRPs, NEMOs and TSOs rely on to nominate cross-border transmission rights correctly, its unchanged republication confirms continuity of operational expectations across all affected borders (including GB interconnectors Eleclink, Nemo Link, IFA1/IFA2 and Viking Link) and the SDAC nomination-deadline postponement logic, reducing uncertainty about whether deadlines or eligible-person rules have shifted since the last capture.

Design impact
Price formation●○○
Cross-border capacity●●●
Liquidity●●○
Operational security●●●
Market participants●●○
Affected markets
long-term transmission rights auctionsday-ahead nomination/SDACintraday auctionsshadow auctions
Who is affected
TSOsBalance Responsible PartiesNEMOsInterconnector operators (Eleclink, Nemo Link, IFA1/IFA2, Viking Link)Market Participants/PTR holders
MD analysis

Treating this as a non-event or confirmation-only update seems appropriate: the absence of any version increment (still v5), unchanged internal document date, and identical structural content suggest this ingestion reflects the same publication rather than a substantive design change. Analysts should continue to treat this as a standing operational reference and reserve DESIGN_CHANGE or IMPLEMENTATION_DETAIL classifications for a future v6 (or later) release that introduces new borders, altered deadlines, or revised nomination principles.

Rule / framework

JAO Nomination Rules (border-specific, legally binding versions referenced as superseding this document); national TSO balancing/transmission agreements; CACM Regulation-based SDAC nomination framework