PJM Proposes Reliability Standards Requiring Large Load Ride-Through During Grid Disturbances

Proposal
ADEQUACY & CAPACITY MARKETSN/ALarge Load interconnection requirementsvoltage and frequency ride-through standardsreliability standards for data centers and crypto-mining loadstransition plans for existing facilitiesFERC Order compliance on Large Load reliability gapsPJM Open Access Transmission Tariff (OATT); FERC Order dated June 18, 2026 directing PJM to identify gaps in Large Load reliability evaluation processes
1Problem identified
2Consultation
3Proposal
4Regulatory review
5Decision
6Implementation
7Go-live
8Market impact
What changed

PJM introduced a proposal at its Sept. 8, 2026 Planning Committee meeting to establish new interconnection reliability standards requiring Large Load facilities (data centers, crypto-mining) to remain connected to the grid ('ride through') during normally cleared transmission system disturbances by meeting minimum voltage and frequency ride-through requirements, rather than disconnecting and switching to backup generation.

Why it matters

The proposal responds to a July 22, 2026 event in which nearly 4,000 MW of data center load unexpectedly disconnected in northern Virginia, causing imbalances and voltage/frequency spikes that PJM and Dominion had to manage. It is the third such measurable event in two years, prompting PJM to call current Large Load operating behavior 'unsustainable.' The standards would directly affect how rapidly growing computational load (data centers, crypto-mining) interconnects with and operates on the PJM system, with implications for system reliability across other ISOs and for FERC-directed tariff reform.

Design impact
Price formation○○○
Cross-border capacity○○○
Liquidity○○○
Operational security●●○
Market participants●○○
Affected markets
PJM Interconnection ProcessPJM Reliability/Ancillary ServicesPJM Transmission Service
Who is affected
Data centersCrypto-mining facilitiesLarge Load transmission customersPJM Transmission Owners (e.g., Dominion, American Electric Power)PJM System Operations
MD analysis

This is a reliability/interconnection design intervention rather than a price-formation mechanism, but it has material market-design consequences: it would impose new technical obligations on Large Load interconnection customers (a growing category of price-inelastic, high-growth demand), potentially affecting interconnection queue processes, capacity accreditation assumptions, and ancillary/reserve requirements tied to unexpected load loss. The FERC order underlying this action signals a broader regulatory push (mirrored by MISO, ERCOT, and NERC) to formalize ride-through and ramp-rate obligations for Large Loads across US markets, which could reshape interconnection tariffs and market participant obligations in PJM and beyond. The transition plan for existing facilities also raises design questions about legacy/grandfathering treatment versus new entrants.

Rule / framework

PJM Open Access Transmission Tariff (OATT); FERC Order dated June 18, 2026 directing PJM to identify gaps in Large Load reliability evaluation processes

Next milestone

PC Special Session – Large Load Ride Through Education · 15 Sept 2026

Primary sources

PJM · ISO · 2026-09-10

PJM Proposes Reliability Standards to Manage Large Load Disconnection Events

Open primary source ↗
pjm-reliability-standards-to-manage-large-load-disconnection-events-proposed-by-pjm