BSC Modification P493 advances through Assessment Procedure to improve Transmission Loss Factor transparency and forecasting
Regulatory reviewBSC Modification P493, raised by Scottish Power on 3 July 2025 following TLF calculation errors exposed by P485, has progressed through six industry Workgroup meetings (August 2025–November 2026) in the Assessment Procedure phase. The Workgroup has agreed a 'staged hybrid' five-year TLF forecasting approach (Elexon-owned model, NESO data/assumptions, consultant support transitioning to an Elexon/NESO-led solution), published an 'in-house' Python Load Flow Model, a TLF Guidance Document, an Analysis Report, and a Power BI exploration tool. The modification is now scheduled for an Assessment Procedure Consultation in December 2026, a further Workgroup meeting in January/February 2027, and presentation of the Assessment Report to the BSC Panel on 11 March 2027, ahead of Report Phase Consultation and a Final Modification Report to the Authority by 17 May 2027.
TLFs directly affect generator settlement revenues and locational cost signals within the Balancing and Settlement Code. Opaque or volatile TLF calculations increase investment risk for generators, particularly those with long-term Contracts for Difference, undermining competition and investor confidence. P493's push for multi-year forecasts, published input data, and clearer methodology documentation is explicitly framed as supporting delivery of the UK's Clean Power 2030 and Net Zero objectives by giving investors greater certainty over future network loss costs.
P493 sits at the intersection of settlement design and investment signalling: by converting an opaque, backward-looking annual TLF calculation into a transparent, forward-looking (five-year) forecasting regime with published Load Flow Model data, it reduces regulatory and revenue uncertainty for generators pricing long-duration CfDs and PPAs. The 'staged hybrid' governance model agreed at Workgroup 5—retaining Elexon ownership of the forecasting model while sourcing NESO system assumptions and consultant methodology support—represents a notable institutional design choice balancing continuity of accountability with technical capability-building ahead of an eventual Elexon/NESO-led steady state. Because TLFs are embedded in BSC settlement calculations across all trading timeframes, improved predictability has second-order effects on locational investment decisions and potentially on transmission charging debates (e.g., interactions with P350 and Section T Annex T-2), without altering core balancing or wholesale price formation mechanics directly.
Balancing and Settlement Code (BSC) Modification process, Great Britain; interacts with BSC Section T Annex T-2 and related P350 guidance
Present Assessment Report to Panel · 11 Mar 2027
Primary sources
BSC Modification P493 Enhancing the TLF transparency and forecasting
Open primary source ↗