PSE opens consultation on Capacity Market Rules amendment RRM/Z/17/2026

Consultation
ADEQUACY & CAPACITY MARKETScapacity market rulebook amendmentshared connection unit definitioncorrected capacity obligationnetwork constraintspenalty and compliance deadlinesassignment of contractual rightsDSO-TSO cooperation
1Problem identified
2Consultation
3Proposal
4Regulatory review
5Decision
6Implementation
7Go-live
8Market impact
What changed

PSE published draft Amendment Card No. RRM/Z/17/2026 to the Capacity Market Rules (Regulamin rynku mocy) on 17 November 2026 and opened a public consultation on changes covering: DSO-TSO cooperation scope related to the Central Energy Market Information System, a new definition of a 'shared connection unit', clarified definition of corrected capacity obligation and network constraint rules, unified deadlines for capacity obligation fulfillment and penalty processes, and new provisions governing assignment of rights and claims under capacity agreements.

Why it matters

These amendments affect how capacity obligations are defined, corrected and enforced in Poland's capacity market, including how shared connections and rights assignment under capacity contracts are treated, which can affect compliance costs, penalty exposure and contractual flexibility for capacity market participants and network operators.

Design impact
Price formation●○○
Cross-border capacity○○○
Liquidity●●○
Operational security●●○
Market participants●●●
Affected markets
Polish Capacity Market
Who is affected
TSO (PSE)DSOsCapacity market participants (capacity providers)Capacity contract holders/financiers
MD analysis

This is an incremental rulebook update to Poland's capacity mechanism rather than a structural redesign, but several elements have operational significance: the shared connection unit definition interacts with distributed/co-located generation and demand response participation, the corrected capacity obligation clarification affects how network constraints are reflected in settlement, and the new cession (assignment) provisions for capacity agreement rights/claims could facilitate secondary market activity or financing structures tied to capacity contracts. The link to the Central Energy Market Information System also signals ongoing data-infrastructure-driven harmonization between DSOs and the TSO. Because this is a national rulebook amendment under the Capacity Market Act legal basis, its direct market design impact is moderate and concentrated on operational/contractual mechanics rather than price formation or cross-border flows.

Rule / framework

Art. 84 ust. 1 of the Act of 8 December 2017 on the Capacity Market (Dz. U. z 2026 r. poz. 1400)

Next milestone

Consultation deadline: comments due 1 December 2026 · 1 Dec 2026