Ei opens stakeholder dialogue on framework for permanent conditional grid connection agreements

Consultation
FLEXIBILITY MARKETSconditional connection agreementspermanent flexible connectiongrid connection capacity managementArticle 6a implementationElectricity Market Directive transpositionArticle 6a of Directive (EU) 2024/1711 amending Directive (EU) 2019/944 (revised Electricity Market Directive)Sweden
1Problem identified
2Consultation
3Proposal
4Regulatory review
5Decision
6Implementation
7Go-live
8Market impact
What changed

Energimarknadsinspektionen (Ei) is revising and expanding its existing position statement on conditional connection agreements (villkorade anslutningsavtal) to add a framework governing when such agreements can be offered as a permanent solution, implementing Article 6a of the revised Electricity Market Directive (EU) 2024/1711. Ei has invited grid companies, electricity users, producers and other stakeholders to a digital EFFEKT-dialogue meeting on 1 December 2026 (09:00-12:00 via Microsoft Teams) to present initial thinking and gather input. Registration for the meeting closes 26 November 2026, and written comments on what the framework should contain can be submitted by email until 4 December 2026.

Why it matters

Conditional connection agreements let a grid company limit how much a connected facility can feed into or draw from the network when capacity is constrained, allowing new connections in areas where the network is otherwise full. Article 6a requires Ei, as the regulatory authority, to establish a framework for offering such agreements in capacity-constrained areas and, where grid expansion is not the most efficient solution, to enable flexible connection agreements as a permanent rather than temporary arrangement. Turning conditional agreements into a durable permanent option would materially change how DSOs manage scarce connection capacity and how producers and consumers plan investments in constrained grid areas, directly shaping flexibility demand and connection economics across Sweden.

Design impact
Price formation○○○
Cross-border capacity○○○
Liquidity●○○
Operational security●●○
Market participants●●○
Affected markets
Electricity grid connection frameworkFlexibility services
Who is affected
Distribution system operatorsElectricity producersElectricity consumersGrid-connected facilities
MD analysis

This is an early-stage framework design process rather than a finalized rule: Ei is still soliciting stakeholder perspectives on the key design parameters (criteria for when agreements should be permanent, and what the framework should contain) before drafting a revised position statement. The direct transposition of Article 6a signals this is part of broader EU-wide implementation of the revised Electricity Market Directive's provisions on flexible/conditional connections, meaning similar frameworks are likely emerging or will emerge from other national regulators. For market design purposes, the critical open question is the boundary condition between grid reinforcement and permanent flexible connection as the 'most efficient solution' — how that boundary is drawn will determine the scale of demand for conditional agreements and their interaction with other flexibility markets and connection queues. The short input window (dialogue meeting December 1, written comments due December 4) suggests Ei intends to move relatively quickly from this consultative phase toward a concrete proposal.

Rule / framework

Article 6a of Directive (EU) 2024/1711 amending Directive (EU) 2019/944 (revised Electricity Market Directive)

Next milestone

Deadline to register for Ei's digital EFFEKT-dialogue meeting on permanent conditional connection agreements · 26 Nov 2026

Primary sources

Energimarknadsinspektionen (Ei) · REGULATOR · 2026-11-23

Påminnelse: Anmäl dig till EFFEKT-dialogen om permanenta villkorade avtal

Open primary source ↗
ei-2026-11-23-paminnelse-anmal-dig-till-effekt-dialogen-om-permanenta-villkorade-av